Energy Efficiency Case Studies
ALCOA NORTH AMERICAN EXTRUSIONS PLANT
Spanish Fork
In July 2000, the Industrial
Assessment Center (IAC) at Colorado State University conducted an energy
assessment at Alcoa’s aluminum extrusion plant in Spanish Fork, Utah. The
purpose of the assessment was to identify, evaluate, and recommend the most
significant opportunities to conserve energy, prevent pollution, and increase
productivity at the facility, while at the same time reducing production costs
and increasing profits.
Alcoa’s plant in Spanish Fork, Utah, produces extruded aluminum products for
the automotive industry, electrical equipment, and miscellaneous other uses
nationwide. About 300 employees are involved in processing 82 million pounds of
extruded products annually. The plant operates 24 hours per day, 7 days per
week, 52 weeks per year.
Manufacturing at the facility includes both casting and extrusion processes.
Process equipment, air compressors, lighting, office cooling, and miscellaneous
loads use electricity to operate. Process furnaces for casting and extrusion, as
well as space heating for the plant, use natural gas.
IAC recommendations were based on observations and measurements made in the
plant. Specific and quantitative recommendations for cost savings, energy
efficiency, pollution prevention, and productivity improvement were identified
where possible. As of September 2002, the following recommendations had been
implemented:
|
Recommendation |
Annual Resource Savings |
Annual Cost Savings ($) |
Implementation Cost ($) |
Payback (years) |
| Turn off melt
burners while charging |
23,455 MMBtu natural gas |
74,960 |
1,050 |
0 |
| Turn off saw
blow-off hose when not in use |
168,200 kWh |
6,150 |
400 |
0.1 |
| Reduce peak
electric demand |
600
kW |
6,360 |
10,000 |
1.6 |
| Reduce compressed
air leaks |
171,900 kWh |
4,980 |
1,000 |
0.2 |
| Install
low-pressure blower for agitation of water quench tank |
114,200 kWh |
4,180 |
6,780 |
1.6 |
| Minimize open time
of melt furnace door |
304
million Btu natural gas |
1,260 |
500 |
0.4 |
| Install dross
press |
198,600 lbs solid waste
238 million Btu natural gas |
107,610 |
75,000 |
0.7 |
| Increase chip
recovery from extrusion saw |
441,900 lbs solid waste |
39,460 |
10,000 |
0.3 |
|
TOTALS |
24,087 million Btu natural gas
454,300 kWh electricity
640,500 lbs solid waste |
244,960 |
104,730 |
0.43 |
The measures implemented to date at the Spanish Fork plant have been
estimated to reduce electric energy consumption by 454,300 kWh/year; reduce
natural gas energy consumption by 24,087 million Btu/year; and reduce
non-hazardous solid waste generation by 640,500 lbs/year. The total cost savings
is estimated to be $244,960 per year, with an implementation cost of $104,730.
Thus, the simple payback period was just over five months. |