Energy Efficiency Guide for Colorado Businesses

Energy Efficiency Case Studies

ALCOA NORTH AMERICAN EXTRUSIONS PLANT

Spanish Fork

ALCOAIn July 2000, the Industrial Assessment Center (IAC) at Colorado State University conducted an energy assessment at Alcoa’s aluminum extrusion plant in Spanish Fork, Utah. The purpose of the assessment was to identify, evaluate, and recommend the most significant opportunities to conserve energy, prevent pollution, and increase productivity at the facility, while at the same time reducing production costs and increasing profits.

Alcoa’s plant in Spanish Fork, Utah, produces extruded aluminum products for the automotive industry, electrical equipment, and miscellaneous other uses nationwide. About 300 employees are involved in processing 82 million pounds of extruded products annually. The plant operates 24 hours per day, 7 days per week, 52 weeks per year.

Manufacturing at the facility includes both casting and extrusion processes. Process equipment, air compressors, lighting, office cooling, and miscellaneous loads use electricity to operate. Process furnaces for casting and extrusion, as well as space heating for the plant, use natural gas.

IAC recommendations were based on observations and measurements made in the plant. Specific and quantitative recommendations for cost savings, energy efficiency, pollution prevention, and productivity improvement were identified where possible. As of September 2002, the following recommendations had been implemented:

Recommendation Annual Resource Savings Annual Cost Savings ($) Implementation Cost ($) Payback (years)
Turn off melt burners while charging 23,455 MMBtu natural gas 74,960 1,050 0
Turn off saw blow-off hose when not in use 168,200 kWh 6,150 400 0.1
Reduce peak electric demand 600 kW 6,360 10,000 1.6
Reduce compressed air leaks 171,900 kWh 4,980 1,000 0.2
Install low-pressure blower for agitation of water quench tank 114,200 kWh 4,180 6,780 1.6
Minimize open time of melt furnace door 304 million Btu natural gas 1,260 500 0.4
Install dross press 198,600 lbs solid waste
238 million Btu natural gas
107,610 75,000 0.7
Increase chip recovery from extrusion saw 441,900 lbs solid waste 39,460 10,000 0.3
TOTALS 24,087 million Btu natural gas
454,300 kWh electricity
640,500 lbs solid waste
244,960 104,730 0.43

The measures implemented to date at the Spanish Fork plant have been estimated to reduce electric energy consumption by 454,300 kWh/year; reduce natural gas energy consumption by 24,087 million Btu/year; and reduce non-hazardous solid waste generation by 640,500 lbs/year. The total cost savings is estimated to be $244,960 per year, with an implementation cost of $104,730. Thus, the simple payback period was just over five months.


Why Care About Energy Efficiency? | Steps to Saving Energy & Money | Recommendations by Sector
Energy Efficiency Measures | Assistance | Program Profiles | Case Studies | Glossary of Energy Terms | Home

© 2006 Southwest Energy Efficiency Project
2260 Baseline Road, Suite 212, Boulder, CO 80302
(303) 447-0078 fax: (303) 786-8054 info@swenergy.org